EVM Calculator

Enter your project's Budget at Completion, planned percent complete, actual percent complete, and actual cost to get Planned Value, Earned Value, cost and schedule variances, performance indexes, and a forecast at completion.

Quick Facts

Core formulas
PV = BAC × planned %, EV = BAC × actual %
Cost Variance = EV − AC; Schedule Variance = EV − PV.
Performance indexes
CPI = EV ÷ AC, SPI = EV ÷ PV
A value above 1.0 is favorable; below 1.0 signals overspending or schedule slippage.
Forecast
EAC = BAC ÷ CPI
The standard CPI-based estimate, assuming current cost performance continues.

Your Results

Calculated
Cost Performance Index (CPI)
-
EV ÷ AC — cost efficiency
Schedule Performance Index (SPI)
-
EV ÷ PV — schedule efficiency
Estimate at Completion (EAC)
-
Forecast total cost: BAC ÷ CPI
Variance at Completion (VAC)
-
Projected surplus or overrun: BAC − EAC

Ready

Enter BAC, planned % complete, actual % complete, and actual cost, then press Calculate.

How the EVM Calculator works

Earned Value Management (EVM) is the standard technique project managers use to check whether a project is on budget and on schedule by comparing three numbers at a single point in time: the value of work that was planned, the value of work actually completed, and the money actually spent. This calculator takes your project's Budget at Completion together with a planned and an actual percent-complete figure, plus actual cost, and derives the full set of standard EVM metrics from them.

The base measures

Planned Value (PV) = Budget at Completion (BAC) × planned percent complete — the value of work that was scheduled to be done by now. Earned Value (EV) = BAC × actual percent complete — the value of work actually completed, valued at its budgeted cost. Actual Cost (AC) is what has genuinely been spent so far, entered directly.

Variances and performance indexes

Cost Variance (CV) = EV − AC. A negative CV means the work performed cost more than it was budgeted for. Schedule Variance (SV) = EV − PV. A negative SV means less work has been completed than was planned. The Cost Performance Index (CPI) = EV ÷ AC and Schedule Performance Index (SPI) = EV ÷ PV express the same relationships as ratios: a value of 1.0 is exactly on plan, above 1.0 is favorable, and below 1.0 signals overspending or a schedule slip.

Forecasting the finish

The calculator forecasts the total project cost with the standard CPI-based formula: Estimate at Completion (EAC) = BAC ÷ CPI, which assumes the cost efficiency observed so far continues for the remaining work. From that, Estimate to Complete (ETC) = EAC − AC is the money still needed, and Variance at Completion (VAC) = BAC − EAC is the projected surplus (positive) or overrun (negative) against the original budget. A related index, To-Complete Performance Index (TCPI) = (BAC − EV) ÷ (BAC − AC), is the cost efficiency the remaining work would need to hit in order to still finish on the original budget.

Worked example

A $100,000 project (BAC) was scheduled to be 50% complete by now (PV = $50,000) but is actually only 45% complete (EV = $45,000), with $52,000 already spent (AC). That gives CV = $45,000 − $52,000 = −$7,000 (over budget) and SV = $45,000 − $50,000 = −$5,000 (behind schedule). CPI = 45,000 ÷ 52,000 ≈ 0.87 and SPI = 45,000 ÷ 50,000 = 0.90 — both below 1.0, so the project is spending inefficiently and running late. EAC = BAC ÷ CPI = $100,000 ÷ (45,000 ÷ 52,000) ≈ $115,556, meaning the project is forecast to finish about $15,556 over its original budget (VAC ≈ −$15,556) if current cost performance does not improve.

Assumptions and limits

This calculator derives PV and EV from a simple percent-complete estimate against the total budget, which is a common and standard approach when a detailed cost-baseline schedule is not available. If your organization tracks PV and EV directly from a time-phased budget or a weighted milestone schedule, use those figures as the source of the percent-complete inputs for a more precise result. EVM is a cost-and-schedule diagnostic, not a substitute for qualitative risk review, scope management, or contractual reporting requirements.

Frequently Asked Questions

What is Earned Value Management (EVM)?
EVM is a project management technique that compares the value of work actually completed (Earned Value) against the value of work that was planned (Planned Value) and the money actually spent (Actual Cost). Comparing these three figures shows whether a project is ahead of or behind schedule, and under or over budget, at any point in time.
How are Planned Value and Earned Value calculated?
Planned Value (PV) = Budget at Completion (BAC) x planned percent complete. Earned Value (EV) = BAC x actual percent complete. For example, a $100,000 project that was scheduled to be 50% done (PV = $50,000) but is actually 45% done (EV = $45,000) is behind its plan even before actual cost is considered.
What do CPI and SPI mean?
The Cost Performance Index (CPI = EV / AC) measures cost efficiency: a CPI above 1.0 means the project is delivering more value than it is spending. The Schedule Performance Index (SPI = EV / PV) measures schedule efficiency: an SPI above 1.0 means more work has been completed than was planned by this point. Values below 1.0 signal overspending or schedule slippage.
How is the Estimate at Completion (EAC) calculated?
This calculator uses the standard CPI-based forecast: EAC = BAC / CPI, which assumes the cost performance seen so far will continue for the rest of the project. Estimate to Complete (ETC) is EAC minus Actual Cost, and Variance at Completion (VAC) is BAC minus EAC — a negative VAC signals a projected budget overrun.