How the Burndown Chart Calculator works
A burndown chart tracks how much work remains in a sprint or project over time, plotting an "ideal" straight-line pace against the team's actual progress. This calculator applies the standard Agile/Scrum burndown formulas to your inputs so you can see, at a glance, whether the team is ahead, on track, or behind the pace needed to finish on schedule.
The formulas
For a total scope S (story points or hours), a sprint length of D days, E days elapsed, and C points completed so far:
Ideal burn rate = S ÷ D
Ideal remaining = S − (Ideal burn rate × E)
Actual remaining = S − C
Required velocity = Actual remaining ÷ (D − E)
Ideal remaining is the point on the straight diagonal "ideal line" that a textbook burndown chart draws from the total scope on day 0 down to zero on the last day. Actual remaining is where the team really stands. Comparing the two shows the schedule variance; dividing that gap by the ideal burn rate converts it into "days of work" ahead or behind.
Worked example
Take a two-week sprint with 200 story points of scope (D = 20 working days), 8 days elapsed, and 70 points completed. The ideal burn rate is 200 ÷ 20 = 10 points/day, so ideal remaining at day 8 is 200 − (10 × 8) = 120 points. Actual remaining work is 200 − 70 = 130 points — 10 points, or exactly one day of ideal pace, behind schedule. With 12 days left (20 − 8), finishing on time now requires 130 ÷ 12 ≈ 10.83 points/day, slightly above the original 10 points/day ideal pace.
Reading the schedule variance
- Actual remaining below ideal remaining: the team is ahead of the ideal line.
- Actual remaining equal to ideal remaining: the team is exactly on the ideal pace.
- Actual remaining above ideal remaining: the team is behind the ideal line and needs a higher velocity than originally planned to still finish on time.
What the projected finish means
The projected finish uses the team's actual velocity so far (completed points ÷ days elapsed) and asks how many days it would take to clear the full scope at that same pace. It is only a projection — early-sprint days carry a lot of noise, so treat a projection made on day one or two with caution and re-check it as more days of real data accumulate.